Question 573 - PMP discussion
A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.
What should the project manager do?
A.
Talk to the team member to determine why their performance changed.
B.
Talk to the team member's manager to provide more training.
C.
Talk to the team member and a human resources (HR) representative.
D.
Talk to the project lead and ask them to allocate less demanding tasks.
Your answer: