After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.
What should the project manager do?
A.
Change the kick-off meeting to a virtual meeting so all can attend at the same time.
B.
Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project.
C.
Reschedule the kick-off meeting for the following month so all can attend on-site.
D.
Make arrangements for the stakeholder to join the kick-off meeting virtually.