At the end of a project, the project manager was asked to provide a performance rating of the project team members.

What should the project manager mainly make reference to?

A.
Input from project stakeholders
Answers
A.
Input from project stakeholders
B.
Feedback from the project sponsor
Answers
B.
Feedback from the project sponsor
C.
Agreed-upon key performance indicators (KPIs)
Answers
C.
Agreed-upon key performance indicators (KPIs)
D.
Competencies of team members
Answers
D.
Competencies of team members
Suggested answer: C