A project manager prepared a project benefits management plan.

Which of the following should be included in this document?

A.
Strategic alignment, benefits owner, risk register
Answers
A.
Strategic alignment, benefits owner, risk register
B.
Target benefits, benefits owner, lessons learned
Answers
B.
Target benefits, benefits owner, lessons learned
C.
Project requirements, target benefits, issue log, metrics
Answers
C.
Project requirements, target benefits, issue log, metrics
D.
Target benefits, strategic alignment, time frame for realizing benefits
Answers
D.
Target benefits, strategic alignment, time frame for realizing benefits
Suggested answer: D