In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and D. Country B discovers that one of the legal requirements was not addressed.
What should the project manager have done to avoid this situation?
A.
Managed risk mitigation strategies specific to each country.
B.
Asked procurement to assign resources located in each country.
C.
Selected countries that had similar regulatory requirements.
D.
Identified the regulatory differences among the countries.
Your answer: