List of questions
Related questions
Question 586 - PMP discussion
In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?
A.
Escalate to management for approval since the change was not included in the original requirements.
B.
Tell the customer that the requirement change will be put into the next project phase if management approves.
C.
Give the change to the scrum master to investigate how much additional effort the change will require.
D.
Validate the requirement change with the product owner and development team before redefining the scope.
Your answer:
0 comments
Sorted by
Leave a comment first