Question 598 - PMP discussion

Report
Export

A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?

A.
Explain to the team that open discussions are needed but remind the team to follow the ground rules.
Answers
A.
Explain to the team that open discussions are needed but remind the team to follow the ground rules.
B.
Ask this member to only discuss the current topic to achieve team efficiency.
Answers
B.
Ask this member to only discuss the current topic to achieve team efficiency.
C.
Ask the team to accept the input from this particular member as their input may be useful.
Answers
C.
Ask the team to accept the input from this particular member as their input may be useful.
D.
Allow the self-organized team to discuss the situation among themselves and come to a resolution.
Answers
D.
Allow the self-organized team to discuss the situation among themselves and come to a resolution.
Suggested answer: A