Question 599 - PMP discussion
A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.
Which scheduling method should the project manager use to develop the schedule?
A.
Analogous scheduling
B.
Three-point scheduling
C.
Iterative scheduling
D.
Parametric scheduling
Your answer: