A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.

Which scheduling method should the project manager use to develop the schedule?

A.
Analogous scheduling
Answers
A.
Analogous scheduling
B.
Three-point scheduling
Answers
B.
Three-point scheduling
C.
Iterative scheduling
Answers
C.
Iterative scheduling
D.
Parametric scheduling
Answers
D.
Parametric scheduling
Suggested answer: C