Question 602 - PMP discussion
A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.
What should the project manager do?
A.
Invite the stakeholders to discuss prioritization of a new deliverable.
B.
Detail the reason for the deliverable delay in the status report.
C.
Register a risk and escalate it to the project sponsor.
D.
Include the responsibility for acquisition with the core team.