ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 603 - PMP discussion

Report
Export

A project manager works in a matrix organization and is managing an internal software development project that is intended to reduce conflicts in the company's internal tracking system. During development, the project manager is informed that the software has to account for an unexpected change to government accounting requirements. The development team was able to make the change with no additional cost; however, the project manager notices that the testing costs are beginning to exceed the testing budget.

What should the project manager do?

A.
Ask the project sponsor to allocate funds from the contingency reserve to fund the additional testing.
Answers
A.
Ask the project sponsor to allocate funds from the contingency reserve to fund the additional testing.
B.
Conduct a cost-benefit analysis to determine if the funds can be reallocated from the development team.
Answers
B.
Conduct a cost-benefit analysis to determine if the funds can be reallocated from the development team.
C.
Submit a change request to the cost baseline through the governance process to fund the additional testing.
Answers
C.
Submit a change request to the cost baseline through the governance process to fund the additional testing.
D.
Update the basis of estimates and the cost management plan to track the additional funding required for testing.
Answers
D.
Update the basis of estimates and the cost management plan to track the additional funding required for testing.
Suggested answer: C
asked 23/09/2024
Ahmed Khan
47 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first