Question 604 - PMP discussion

Report
Export

A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?

A.
Discuss ground rules with the team that will include daily meetings.
Answers
A.
Discuss ground rules with the team that will include daily meetings.
B.
Agree on a new time and reschedule the daily standups.
Answers
B.
Agree on a new time and reschedule the daily standups.
C.
Use one-to-one virtual meetings because they are more efficient.
Answers
C.
Use one-to-one virtual meetings because they are more efficient.
D.
Ask senior management for coaching regarding this situation.
Answers
D.
Ask senior management for coaching regarding this situation.
Suggested answer: A