A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?

A.
Organizational process assets (OPAs)
Answers
A.
Organizational process assets (OPAs)
B.
Quality process
Answers
B.
Quality process
C.
Project charter
Answers
C.
Project charter
D.
Quality management plan
Answers
D.
Quality management plan
Suggested answer: D

Explanation:

The manager is aware of the organization standards, so he needs to review the quality management plan to see why they have not been included in the plan. It is not about what the standards are, it is about why deliverables are not satisfying those standards.

Explanation:

asked 23/09/2024