Question 615 - PMP discussion
A highly critical project is in jeopardy due to missing professional resources.
What should the newly assigned project manager do first?
A.
Find available professionals within the organization to fill the gaps.
B.
Determine the possibility for team members to split up the required tasks.
C.
Allocate funding for seeking external professionals to fill the gaps.
D.
Request additional budget for team training for the missing expertise.