Question 616 - PMP discussion
Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.
What should the project manager do next to address this issue?
A.
Obtain and implement the sponsor's recommendations for a solution.
B.
Ask the team members to proceed independently while examining needs and alternatives.
C.
Place a hold on activities until the team can resume the work on-site.
D.
Halt all processes until procurement and implementation of solutions are completed.
Your answer: