List of questions
Related questions
Question 617 - PMP discussion
A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback.
One of them has not provided any feedback despite numerous requests from the team.
What should the project manager do in this situation?
A.
Explain to the sponsor why the reluctant stakeholder needs to provide feedback.
B.
Host a meeting with the reluctant stakeholder and project team to resolve any conflict.
C.
Meet with all seven of the project stakeholders and request all of their feedback.
D.
Schedule a meeting with the reluctant project stakeholder to obtain their feedback.
Your answer:
0 comments
Sorted by
Leave a comment first