A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?

A.
Ask for help to increase the team capacity to deliver on time.
Answers
A.
Ask for help to increase the team capacity to deliver on time.
B.
Ask for a project extension to deliver the committed scope.
Answers
B.
Ask for a project extension to deliver the committed scope.
C.
Update the issue log and escalate the problem to the project sponsor.
Answers
C.
Update the issue log and escalate the problem to the project sponsor.
D.
Review the options and possible solutions with the project team.
Answers
D.
Review the options and possible solutions with the project team.
Suggested answer: D