Question 620 - PMP discussion
A project charter has been approved and the project manager has been assigned to the project.
The project manager is currently working with the project team to subdivide the project work packages.
What is the project manager doing?
A.
Resource leveling
B.
Work breakdown structure (WBS)
C.
Decomposition
D.
Network diagram