Question 622 - PMP discussion
A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.
Who should determine which artifacts should be used in the project?
A.
The project stakeholders should meet and determine the project artifacts to be used by the project manager and the project management team.
B.
The project manager and project management team should use the standard project artifacts from the database.
C.
The project sponsor should select the project artifacts that the project manager and project management team should use in the project.
D.
The project manager and the project management team should select the appropriate artifacts for use in the specific project.