An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?

A.
Statement of work (SOW)
Answers
A.
Statement of work (SOW)
B.
Business case
Answers
B.
Business case
C.
Product backlog
Answers
C.
Product backlog
D.
Solution architecture
Answers
D.
Solution architecture
Suggested answer: B