ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 624 - PMP discussion

Report
Export

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

A.
Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.
Answers
A.
Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.
B.
Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.
Answers
B.
Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.
C.
Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.
Answers
C.
Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.
D.
Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.
Answers
D.
Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.
Suggested answer: C
asked 23/09/2024
Giulia Maggio
38 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first