An organization embarking on a significant transformation initiated a project to improve and document business processes. One of the objectives of the project is to implement agile project delivery.

What is the main reason for adopting agile?

A.
Projects will be completed faster, saving time and money.
Answers
A.
Projects will be completed faster, saving time and money.
B.
Projects will be delivered with very low risk to the organization.
Answers
B.
Projects will be delivered with very low risk to the organization.
C.
Projects will deliver early and use value based on priority.
Answers
C.
Projects will deliver early and use value based on priority.
D.
Projects will be delivered with significant cost savings.
Answers
D.
Projects will be delivered with significant cost savings.
Suggested answer: C