A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.
What should the project manager do first?
A.
Discuss the requested change with the sponsor.
B.
Evaluate the cost of the additional requested work.
C.
Discuss the requested change with the team.
D.
Evaluate the impact and submit a change request.