ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 629 - PMP discussion

Report
Export

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.

What should the project manager do first?

A.
Discuss the requested change with the sponsor.
Answers
A.
Discuss the requested change with the sponsor.
B.
Evaluate the cost of the additional requested work.
Answers
B.
Evaluate the cost of the additional requested work.
C.
Discuss the requested change with the team.
Answers
C.
Discuss the requested change with the team.
D.
Evaluate the impact and submit a change request.
Answers
D.
Evaluate the impact and submit a change request.
Suggested answer: C
asked 23/09/2024
Arushi Rastogi
29 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first