A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

A.
Check the alternative resources available in the organization for the request.
Answers
A.
Check the alternative resources available in the organization for the request.
B.
Confirm that the budget and resources are available to execute the work request.
Answers
B.
Confirm that the budget and resources are available to execute the work request.
C.
Evaluate the nature of the request and plan communication accordingly.
Answers
C.
Evaluate the nature of the request and plan communication accordingly.
D.
Submit a change request and allocate the budget and resources needed for execution.
Answers
D.
Submit a change request and allocate the budget and resources needed for execution.
Suggested answer: C