Question 631 - PMP discussion
A project manager is scheduled to meet with a client for their weekly risk management meeting.
The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two.)
A.
Discuss the issue with the external supplier's authority.
B.
Gather additional information and estimate the impact.
C.
Wait for the client to raise a concern and collect more information.
D.
Review the lessons learned from similar past projects.
E.
Update the risk log and bring this up in the meeting with the client.