Question 632 - PMP discussion
A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.
What should the project manager do?
A.
Ask the new team member to focus only on development and not do the testing.
B.
Coach the new team member to conduct the testing the way it has always been done for this project.
C.
Schedule a meeting with the new team member to learn about the new method of testing.
D.
Request that the new team member do the testing the way it has always been done for this project.
Your answer: