A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.

What should the project manager do to avoid similar complaints?

A.
Send a shorter daily report to this steering committee member.
Answers
A.
Send a shorter daily report to this steering committee member.
B.
Demonstrate the weekly reports in a presentation for the steering committee member.
Answers
B.
Demonstrate the weekly reports in a presentation for the steering committee member.
C.
Verify the information needed for steering committee members.
Answers
C.
Verify the information needed for steering committee members.
D.
Present the status at a weekly meeting with the steering committee.
Answers
D.
Present the status at a weekly meeting with the steering committee.
Suggested answer: C