ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 643 - PMP discussion

Report
Export

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract. Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

A.
Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.
Answers
A.
Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.
B.
Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.
Answers
B.
Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.
C.
Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.
Answers
C.
Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.
D.
Submit a request for extra time and budget related to the dependencies and technical difficulties.
Answers
D.
Submit a request for extra time and budget related to the dependencies and technical difficulties.
Suggested answer: A
asked 23/09/2024
Thiago B
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first