Question 644 - PMP discussion

Report
Export

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

A.
Organize an online distribution channel from another country.
Answers
A.
Organize an online distribution channel from another country.
B.
Ask the sponsor to authorize the launch and then wait for approval.
Answers
B.
Ask the sponsor to authorize the launch and then wait for approval.
C.
Ask the board to use their influence and speed up the approval.
Answers
C.
Ask the board to use their influence and speed up the approval.
D.
Work with the team to find ways to bypass the regulations.
Answers
D.
Work with the team to find ways to bypass the regulations.
Suggested answer: B