While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers.

What should the project manager do?

A.
Apply for a formal change control board (CCB) approval.
Answers
A.
Apply for a formal change control board (CCB) approval.
B.
Discuss this with the functional manager and related parties.
Answers
B.
Discuss this with the functional manager and related parties.
C.
Reject the functional manager's change request immediately.
Answers
C.
Reject the functional manager's change request immediately.
D.
Analyze the impact of the change request on the project.
Answers
D.
Analyze the impact of the change request on the project.
Suggested answer: D