A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.
What should the project manager do next?
A.
Discuss the issue with the team member in a one-on-one meeting.
B.
Escalate the performance issue to the team member's functional manager.
C.
Ask the team member to justify the delay during a team meeting.
D.
Review the human resources (HR) policies for relevant corrective actions.