ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 667 - PMP discussion

Report
Export

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

A.
Ask the project team to keep developing other tasks that do not depend on the purchase of services.
Answers
A.
Ask the project team to keep developing other tasks that do not depend on the purchase of services.
B.
Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.
Answers
B.
Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.
C.
Request that the purchasing tasks be outsourced through an existing purchasing vendor.
Answers
C.
Request that the purchasing tasks be outsourced through an existing purchasing vendor.
D.
Modify the project schedule to accommodate the delays in the purchase of services.
Answers
D.
Modify the project schedule to accommodate the delays in the purchase of services.
Suggested answer: B
asked 23/09/2024
Louis Flink
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first