A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?

A.
Suggest that the team member contact the IT department.
Answers
A.
Suggest that the team member contact the IT department.
B.
Update the issue log and escalate the problem to the product owner.
Answers
B.
Update the issue log and escalate the problem to the product owner.
C.
Ask the other team members to step in and do the work.
Answers
C.
Ask the other team members to step in and do the work.
D.
Facilitate a priority resolution of the issue with the IT department.
Answers
D.
Facilitate a priority resolution of the issue with the IT department.
Suggested answer: D