A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
A.
Definitive estimate
B.
Order of magnitude
C.
Budget estimate
D.
Story points
Your answer: