Question 671 - PMP discussion

Report
Export

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?

A.
Contact the vendor that supplied similar equipment for a previous project.
Answers
A.
Contact the vendor that supplied similar equipment for a previous project.
B.
Use the existing equipment and replace it later with the new equipment.
Answers
B.
Use the existing equipment and replace it later with the new equipment.
C.
Ask the project sponsor to expedite the vendor selection process.
Answers
C.
Ask the project sponsor to expedite the vendor selection process.
D.
Work with the procurement team to find alternative options.
Answers
D.
Work with the procurement team to find alternative options.
Suggested answer: D