Question 671
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.
What should the project manager do?
Question 672
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users' quality requirements.
What should the project lead recommend?
Question 673
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.
What should the project manager do?
Question 674
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a conflicting operational schedule.
What should the project manager do?
Explanation:
The team member himself cannot prioritize tasks or schedules. Team members are guided by their managers and in this case the team member has other obligations. The PM needs to speak to the functional manager to see if he can assign those tasks to someone else or he can work on those later. It is the functional manager's call to decide how to utilize the resource.
Explanation:
Question 675
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is working on a large IT project. During a review for one of the deliverables. a stakeholder raised a concern about the final product.
What should the project manager do first?
Question 676
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.
What should the project manager do next?
Question 677
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is leading a project team composed of members with varying levels of knowledge and experience. Some are experts and some have less than 1 year of experience.
The project schedule was approved by the steering committee.
What should the project manager do?
Question 678
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.
What should the project manager review during the management review to ensure the meeting is effective?
Question 679
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During the service procurement process for a strategic project, only one bidder submitted a bid.
The price of the offer is significantly large and the project sponsor is not I convinced that the return on investment (ROI) can be achieved.
How should the project manager address this issue?
Explanation:
The project manager should first revisit the project charter and assess if the project goals and objectives can be met with other alternatives. This could include re-evaluating the project requirements, researching other suppliers and/or re-designing the project in order to reduce the cost. If all other alternatives are exhausted, then the project manager should seek approval from the project sponsor or the CEO to proceed with the purchase order.
Explanation:
Question 680
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager leads a project that implements a new process throughout the organization.
The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.
What should the project manager do?
Question