PMI PMP Practice Test - Questions Answers, Page 67
List of questions
Related questions
While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers.
What should the project manager do?
A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.
What should the project manager do next?
A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk. The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.
Which document should the project manager review with their team?
A project manager is leading a cross-departmental project that involves many stakeholders.
During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.
What should the project manager do to integrate the diverse stakeholder groups?
A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change.
What should the project manager do?
A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.
What should the project manager do?
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
A project manager was recently assigned to rescue a high-priority project for an Olympic facility.
The project is behind schedule. with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.
What should the project manager do first?
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
Question