Question 641

Report Export Collapse

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax.

Which approach should the project manager take to implement this amendment?

Become a Premium Member for full access
  Unlock Premium Member

Question 642

Report Export Collapse

A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint.

How should the project manager help the team resolve the issue?

Become a Premium Member for full access
  Unlock Premium Member

Question 643

Report Export Collapse

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract. Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 644

Report Export Collapse

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 645

Report Export Collapse

A project manager notices that a new junior team member's suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 646

Report Export Collapse

A project manager is leading a project with strict time constraints. In team meetings, one of the team members is always silent. The project manager determines that this team member is not knowledgeable about the technology solution.

The project manager is concerned that this problem will impact productivity.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 647

Report Export Collapse

A project manager is assigned to a new project. The project is for a new product that the company wants to launch as soon as possible to test market readiness. The project is part of a large business transformation, and the objective is to open delivery channels for the new product.

Which delivery approach should the project manager recommend?

Become a Premium Member for full access
  Unlock Premium Member

Question 648

Report Export Collapse

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

Become a Premium Member for full access
  Unlock Premium Member

Question 649

Report Export Collapse

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 650

Report Export Collapse

A project team is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.

What should the project manager do?

Become a Premium Member for full access