ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 64

Add to Whishlist

List of questions

Question 631

Report Export Collapse

A project manager is scheduled to meet with a client for their weekly risk management meeting.

The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 632

Report Export Collapse

A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 633

Report Export Collapse

A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.

What should the project manager do to avoid similar complaints?

Become a Premium Member for full access
  Unlock Premium Member

Question 634

Report Export Collapse

All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

Become a Premium Member for full access
  Unlock Premium Member

Question 635

Report Export Collapse

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product.

Which approach should the project manager take?

Become a Premium Member for full access
  Unlock Premium Member

Question 636

Report Export Collapse

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager.

This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 637

Report Export Collapse

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

Become a Premium Member for full access
  Unlock Premium Member

Question 638

Report Export Collapse

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

Become a Premium Member for full access
  Unlock Premium Member

Question 639

Report Export Collapse

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 640

Report Export Collapse

A company's key product is evolving and requires the use of a new technology. No one on the team is familiar with this technology; however, experienced developers on the team volunteered to study the concepts and application and believe they will be able to take full responsibility for the new technology.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions