A project manager is scheduled to meet with a client for their weekly risk management meeting.

The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two.)

A.
Discuss the issue with the external supplier's authority.
A.
Discuss the issue with the external supplier's authority.
Answers
B.
Gather additional information and estimate the impact.
B.
Gather additional information and estimate the impact.
Answers
C.
Wait for the client to raise a concern and collect more information.
C.
Wait for the client to raise a concern and collect more information.
Answers
D.
Review the lessons learned from similar past projects.
D.
Review the lessons learned from similar past projects.
Answers
E.
Update the risk log and bring this up in the meeting with the client.
E.
Update the risk log and bring this up in the meeting with the client.
Answers
Suggested answer: B, E

A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.

What should the project manager do?

A.
Ask the new team member to focus only on development and not do the testing.
A.
Ask the new team member to focus only on development and not do the testing.
Answers
B.
Coach the new team member to conduct the testing the way it has always been done for this project.
B.
Coach the new team member to conduct the testing the way it has always been done for this project.
Answers
C.
Schedule a meeting with the new team member to learn about the new method of testing.
C.
Schedule a meeting with the new team member to learn about the new method of testing.
Answers
D.
Request that the new team member do the testing the way it has always been done for this project.
D.
Request that the new team member do the testing the way it has always been done for this project.
Answers
Suggested answer: C

A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.

What should the project manager do to avoid similar complaints?

A.
Send a shorter daily report to this steering committee member.
A.
Send a shorter daily report to this steering committee member.
Answers
B.
Demonstrate the weekly reports in a presentation for the steering committee member.
B.
Demonstrate the weekly reports in a presentation for the steering committee member.
Answers
C.
Verify the information needed for steering committee members.
C.
Verify the information needed for steering committee members.
Answers
D.
Present the status at a weekly meeting with the steering committee.
D.
Present the status at a weekly meeting with the steering committee.
Answers
Suggested answer: C

All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

A.
Meet with the team in 2 weeks to respond to all of the open tasks.
A.
Meet with the team in 2 weeks to respond to all of the open tasks.
Answers
B.
Review the Pareto diagram to identify the source of delays.
B.
Review the Pareto diagram to identify the source of delays.
Answers
C.
Delegate the decision-making authority of some tasks to the team.
C.
Delegate the decision-making authority of some tasks to the team.
Answers
D.
Consolidate the decision-making authority to remain with the project manager.
D.
Consolidate the decision-making authority to remain with the project manager.
Answers
Suggested answer: C

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product.

Which approach should the project manager take?

A.
Ask the team to raise blockers or impediments in daily meetings.
A.
Ask the team to raise blockers or impediments in daily meetings.
Answers
B.
Prioritize the tasks with high risks to reduce the number of iterations required.
B.
Prioritize the tasks with high risks to reduce the number of iterations required.
Answers
C.
Ask the team to challenge the project estimations for a faster delivery.
C.
Ask the team to challenge the project estimations for a faster delivery.
Answers
D.
Prioritize deliverables based on business value and define frequent releases.
D.
Prioritize deliverables based on business value and define frequent releases.
Answers
Suggested answer: D

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager.

This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

A.
Ask the financial manager to delay implementation due to potential project delays and penalties.
A.
Ask the financial manager to delay implementation due to potential project delays and penalties.
Answers
B.
Assess the impact of the change and review the project management plan for next steps.
B.
Assess the impact of the change and review the project management plan for next steps.
Answers
C.
Adapt the resource management plan and ask for financial approval before sending it to the customer.
C.
Adapt the resource management plan and ask for financial approval before sending it to the customer.
Answers
D.
Review the project schedule to determine which technique will reduce impact on project duration.
D.
Review the project schedule to determine which technique will reduce impact on project duration.
Answers
Suggested answer: B

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

A.
Probabilistic analysis was used to develop the budget to address future uncertainties.
A.
Probabilistic analysis was used to develop the budget to address future uncertainties.
Answers
B.
The budget was developed by using the lessons learned from previous project data.
B.
The budget was developed by using the lessons learned from previous project data.
Answers
C.
Recurrent team meetings are planned to control the budget against future uncertainties.
C.
Recurrent team meetings are planned to control the budget against future uncertainties.
Answers
D.
Feedback from stakeholders will be addressed at each board meeting to adapt the budget.
D.
Feedback from stakeholders will be addressed at each board meeting to adapt the budget.
Answers
Suggested answer: B

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

A.
Facilitated cross-functional knowledge transfer during the project.
A.
Facilitated cross-functional knowledge transfer during the project.
Answers
B.
Acquired more than one resource skilled in each component.
B.
Acquired more than one resource skilled in each component.
Answers
C.
Outsourced development of the specific component to another team.
C.
Outsourced development of the specific component to another team.
Answers
D.
Requested robust documentation for the component's build.
D.
Requested robust documentation for the component's build.
Answers
Suggested answer: A

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

A.
Explain to the stakeholder that these are the approved templates for the reports.
A.
Explain to the stakeholder that these are the approved templates for the reports.
Answers
B.
Ask the project team to review and modify all of these reports.
B.
Ask the project team to review and modify all of these reports.
Answers
C.
Ensure that the reports comply with the communications management plan.
C.
Ensure that the reports comply with the communications management plan.
Answers
D.
Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.
D.
Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.
Answers
Suggested answer: C

A company's key product is evolving and requires the use of a new technology. No one on the team is familiar with this technology; however, experienced developers on the team volunteered to study the concepts and application and believe they will be able to take full responsibility for the new technology.

What should the project manager do?

A.
Outsource the technology work to a third party so as not to delay work.
A.
Outsource the technology work to a third party so as not to delay work.
Answers
B.
Descope this requirement as the developers have more important tasks.
B.
Descope this requirement as the developers have more important tasks.
Answers
C.
Hire externally since the internal developers already have assigned work.
C.
Hire externally since the internal developers already have assigned work.
Answers
D.
Support the developers with their intention to learn the new technology.
D.
Support the developers with their intention to learn the new technology.
Answers
Suggested answer: D

Explanation:

Support the developers with their intention to learn the new technology. Project managers should provide resources and support to the developers to ensure they are successful in their learning and application of the new technology.

Outsourcing the work, descoping the requirement, or hiring externally are not recommended solutions in this case.

Explanation: