A project manager is working on a large IT project. During a review for one of the deliverables. a stakeholder raised a concern about the final product.

What should the project manager do first?

A.
Discuss this with the team and put the stakeholder's concern in the issue log.
Answers
A.
Discuss this with the team and put the stakeholder's concern in the issue log.
B.
Set up a meeting with the sponsor to discuss the details of the deliverable.
Answers
B.
Set up a meeting with the sponsor to discuss the details of the deliverable.
C.
Discuss this with the team and review the project requirements documentation.
Answers
C.
Discuss this with the team and review the project requirements documentation.
D.
Set up a meeting with the product owner to discuss the stakeholder's concern.
Answers
D.
Set up a meeting with the product owner to discuss the stakeholder's concern.
Suggested answer: C