List of questions
Related questions
Question 685 - PMP discussion
During the execution stage. the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.
What should the project manager do first?
A.
Discuss with senior management and seek their guidance.
B.
Discuss with the team and assess the reasons that led to the delay.
C.
Request the team member's manager to find a solution.
D.
Assign more resources from other teams on the late work.
Your answer:
0 comments
Sorted by
Leave a comment first