A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met.

What should the project manager do to meet these requirements?

A.
Ask human resources (HR) to assign a compliance specialist to the team.
Answers
A.
Ask human resources (HR) to assign a compliance specialist to the team.
B.
Determine potential threats regarding compliance with the regulations.
Answers
B.
Determine potential threats regarding compliance with the regulations.
C.
Measure the extent to which the project complies with the regulations.
Answers
C.
Measure the extent to which the project complies with the regulations.
D.
Validate that the software is compliant with standards and regulations.
Answers
D.
Validate that the software is compliant with standards and regulations.
Suggested answer: D