Question 687 - PMP discussion

Report
Export

A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.

What should the project manager do to ensure the project is completed on time with quality?

A.
Meet with the team together and in one-on-one meetings to set clear, shared targets.
Answers
A.
Meet with the team together and in one-on-one meetings to set clear, shared targets.
B.
Encourage the team to participate in a peer evaluation activity by the end of the project.
Answers
B.
Encourage the team to participate in a peer evaluation activity by the end of the project.
C.
Introduce the use of time sheets and ask team members to review and submit them regularly.
Answers
C.
Introduce the use of time sheets and ask team members to review and submit them regularly.
D.
Arrange regular team meetings for the team to update one another on the progress of their assigned tasks.
Answers
D.
Arrange regular team meetings for the team to update one another on the progress of their assigned tasks.
Suggested answer: D