A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.

What should the project manager do?

A.
Suggest that the sponsor conduct a cost-benefit analysis to determine feasibility.
Answers
A.
Suggest that the sponsor conduct a cost-benefit analysis to determine feasibility.
B.
Advise the sponsor that it is not the project manager's job to evaluate the project.
Answers
B.
Advise the sponsor that it is not the project manager's job to evaluate the project.
C.
Use the management reserve in order to expedite completion of the deliverable within 2 months.
Answers
C.
Use the management reserve in order to expedite completion of the deliverable within 2 months.
D.
Change the project methodology in order to achieve completion of the deliverable within 2 months.
Answers
D.
Change the project methodology in order to achieve completion of the deliverable within 2 months.
Suggested answer: A