A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.

What should the project manager do to engage the team?

A.
Invest in a virtual collaboration/colocation environment.
Answers
A.
Invest in a virtual collaboration/colocation environment.
B.
Have one-on-one meetings with team members to improve communication.
Answers
B.
Have one-on-one meetings with team members to improve communication.
C.
Ask human resources (HR) for team-building recommendations.
Answers
C.
Ask human resources (HR) for team-building recommendations.
D.
Schedule weekly team meetings to encourage collaboration.
Answers
D.
Schedule weekly team meetings to encourage collaboration.
Suggested answer: A