Question 699 - PMP discussion

Report
Export

Project progress meetings occur via virtual conference calls. In every project progress meeting, one team member continuously interrupts others during discussions. Other team members often have no opportunity to talk or complete their explanations.

What should the project manager do?

A.
Start the meeting with a review of the ground rules, meeting objectives, and the agenda.
Answers
A.
Start the meeting with a review of the ground rules, meeting objectives, and the agenda.
B.
Speak individually with the team member who always disrupts the conversations.
Answers
B.
Speak individually with the team member who always disrupts the conversations.
C.
Manage time efficiently using the agenda and ask each participant to contribute.
Answers
C.
Manage time efficiently using the agenda and ask each participant to contribute.
D.
Answers
D.
Suggested answer: A

Explanation:

What should the project manager do?

A. Start the meeting with a review of the ground rules, meeting objectives, and the agenda.

B. Speak individually with the team member who always disrupts the conversations.

C. Manage time efficiently using the agenda and ask each participant to contribute.

D. Speak individually with the team members who do not participate in conversations.

Answer: A

Explanation:

asked 23/09/2024