A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.
What should the project manager do to keep the stakeholders engaged?
A.
Use meetings as a communication channel.
B.
Use email as a communication channel.
C.
Use feedback and decision-making tools.
D.
Use a shared collaboration platform.
Your answer: