Question 701 - PMP discussion
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
A.
Inform the project team that they may proceed at a more relaxed pace.
B.
Discuss with the project team alternative options to deliver as planned.
C.
Inform the project team that some of them will work for the vendor.
D.
Discuss with the team the need for longer hours to minimize the impact.
Your answer: