Question 723 - PMP discussion
In a software development project, some of the deliverables do not meet specific performance requirements.
What action should the project manager take?
A.
Review the issues with the project team to address the issues.
B.
Review the requirements traceability matrix at the next meeting.
C.
Report issues to key stakeholders and discuss follow up actions.
D.
Ensure compliance with the quality management plan.