Question 724 - PMP discussion
An experienced, high-performing team has two new team members. After several iterations with the new team members, the project manager noticed that the team's performance has decreased.
What should the project manager do?
A.
Evaluate the two new team members.
B.
Replace the two new team members.
C.
Provide the team with a coaching session.
D.
Allow the teams to organize themselves.