During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected.

What should the project manager have the project team do first to address the issue?

A.
Update the issue log and document the change
Answers
A.
Update the issue log and document the change
B.
Review the product specification requirements.
Answers
B.
Review the product specification requirements.
C.
Perform a root cause analysis
Answers
C.
Perform a root cause analysis
D.
Submit a change request for corrective action.
Answers
D.
Submit a change request for corrective action.
Suggested answer: C