Question 725 - PMP discussion
During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected.
What should the project manager have the project team do first to address the issue?
A.
Update the issue log and document the change
B.
Review the product specification requirements.
C.
Perform a root cause analysis
D.
Submit a change request for corrective action.
Your answer: